Ashridge returned to Pinewood Studios on 19th April 2010 to undertake an external works contract with a very limited 3-week window to complete due to the filming schedule for the new Harry Potter film. The contract, which was completed 2 days early, consisted of the breakout of the existing surface and excavation to reduced levels; sub base and tarmac construction with 6x2 edging along the perimeter. Works also included the installation of gully pots and a drainage run to an existing French drain outfall. | |