Ashridge commenced works as of 14th March 2011 at St Bartholomews School in Newbury. Scroll down to see the latest photos.
This contract with Willmott Dixon is for Phase 4 of this project and consists of the following;
Construction of a 420 metre long RC retaining wall with intergraded RC columns for pitch lighting columns.
PERI Trio formwork used to form wall, incorporating a “Type B” finish as defined by BS8110.
Cut and fill of approximately 6200m3 for the formation of a Multi use games area (MUGA) and Synthetic Turf Pitches (STP) with 2400m3 muck away.
Installation of Storm water drainage works, including 193m3 infiltration tank.
Construction of approx. 400m of permeable and non-permeable asphalt footpaths and a 144 space bike shelter.
Approx. 1100m of electrical ducting for street lighting and CCTV.
Construction of a 50 bay carpark with associated drainage works. | |